QUESTION 21
Which of the following is a definition of an RFP?

A.    A document sent to potential vendors to solicit a bid for a project
B.    A document sent to potential vendors to request information for skills and experience for a project
C.    A document sent to potential vendors to request a commitment for a project
D.    A document sent to potential vendors to solicit information that excludes pricing information for a project (more…)

April 18th, 2018

Posted In: CompTIA, PK0-004 Dumps, PK0-004 Exam Questions, PK0-004 New Questions, PK0-004 PDF, PK0-004 VCE

Tags: , , , , , , ,

Lead2pass CompTIA New Exam PK0-004 VCE Files Free Instant Download:

https://www.lead2pass.com/pk0-004.html

QUESTION 11
If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

A.    The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
B.    The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report
C.    The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW; and then create a status report to provide to the project manager.
D.    The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review

(more…)

March 8th, 2018

Posted In: CompTIA, PK0-004 Dumps, PK0-004 Exam Questions, PK0-004 New Questions, PK0-004 PDF, PK0-004 VCE

Tags: , , , , , , ,

PK0-004 Exam Dumps Free Download In Lead2pass 100% PK0-004 Exam Questions:

https://www.lead2pass.com/pk0-004.html

QUESTION 1
The project manager was asked to provide recommendations for the removal of a vendor.
A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)

A.    The issue log to show why the vendor should be replaced
B.    The team action items to show why the vendor should be replaced
C.    The scope statement to show why the vendor should be replaced
D.    A procurement plan to show why the vendor should be replaced